TORONTO, Aug. 14, 2012 /CNW/ - Gran Colombia Gold Corp. (TSX: GCM)
announced today the release of its unaudited interim condensed
consolidated financial statements for the second quarter ended June 30,
2012 and accompanying management's discussion and analysis. All
financial figures contained herein are expressed in U.S. dollars unless
otherwise noted.
Second Quarter 2012 Highlights
-
Gold production of 25,607 ounces in the second quarter of 2012
represented a 15 percent improvement over the same quarter last year
bringing total gold production for the first half of 2012 to 51,867
ounces, up 21 percent over the first half of last year. After
experiencing some delays in the second quarter, the new ball mill at
Maria Dama came on-line in mid-May. Mill throughput subsequently
increased, reaching an average of 737 tpd in the month of June, a 45
percent increase compared with the first quarter of 2012. Testing of
the new ball mill has proved that it can handle loads of 1,000 tonnes
of ore per day ("tpd"). New flotation cells being installed in the
third quarter as part of the plant upgrade will address the issues that
impacted mill recovery rates in the second quarter, enabling the plant
to handle the increased volumes combined with the much higher grade ore
delivered by the artisanal miners.
-
Revenues of $40.7 million, 47 percent higher than the second quarter of
2011, brought total revenues for the first half of 2012 to $83.4
million. In the first half of 2012, the Company sold 49,232 ounces of
gold at an average realized price of $1,650 per ounce.
-
Consolidated cash cost of $1,313 per ounce of gold sold increased 10
percent from the first quarter of 2012, primarily due to a 10 percent
decrease in the mill recovery rate at Maria Dama at Segovia. Actions
are being taken by management to improve operations at Maria Dama in
the third quarter and to increase production in the second half of the
year at Segovia, which are expected to reduce consolidated cash costs
below $1,100 per ounce by the end of 2012.
-
General and administrative ("G&A") expenses, which include $0.3 million
of one-time advisory fees that helped the Company to begin recovering
overdue VAT claims in Colombia, amounted to $4.2 million and $7.8
million, for the second quarter and first half of 2012, respectively.
G&A expenses in the first half of 2012 represent a 25 percent reduction
compared with the post-merger G&A expenses in the second half of 2011
(G&A in the second quarter and first half of 2011 is not comparable to
the current year as it did not include G&A from Medoro Resources
(Yukon) Inc. ("Medoro") prior to the June 10, 2011 merger).
-
Net loss attributable to shareholders of $13.7 million, or $0.04 per
share, in the second quarter of 2012, includes an impairment charge of
$3.4 million related to the carrying value of its Mazamorras
exploration property after entering into an agreement to sell the
property for total consideration of $5.5 million, $2.9 million of
mark-to-market losses on financial instruments and a $3.3 million
foreign exchange loss.
-
Cash balance at June 30, 2012 was $4.1 million. During the second
quarter of 2012, the Company used $1.0 million of its cash on hand,
together with $3.7 million generated from operating activities and $0.9
million of net proceeds from additional Colombian bank debt facilities
to fund $5.7 million of investing activities during the quarter.
-
Exploration activities in the second quarter included the completion of
a 12,000 metres drilling program at the El Zancudo Project that had
commenced in April 2011. Gran Colombia announced its exploration and
in-fill drilling program had returned high grade gold and silver
mineralization over a strike length of some 450 metres and dip length
of 170 metres on the newly discovered Santa Catalina vein, which is
open in all directions. An updated technical report is expected to be
completed by the end of 2012.
-
A Mineral Resource Estimate announced on June 21, 2012, highlighted an
18 percent increase to 11.8 million ounces of gold and a 26 percent
increase to 80.3 million ounces of silver in the Measured and Indicated
categories at the Company's Marmato Project.
-
Financing: Gran Colombia made further progress in the second quarter
related to a proposed $100 million debt facility to fund the planned
expansion of the Segovia Operations. In addition to supporting the
ongoing due diligence activities of Standard Bank Plc, the Company has
commenced a parallel process to explore competitive proposals from
several other financial institutions.
-
Corporate: During the second quarter of 2012, the Company made several
announcements related to common share purchases made by its Executive
Co-Chairmen, Serafino Iacono and Miguel de la Campa, who increased
their shareholdings to 3.3 percent and 0.9 percent, respectively, in
the issued and outstanding common shares of the Company.
Commenting on the Company's progress in the second quarter of 2012,
Maria Consuelo Araujo, Chief Executive Officer of the Company, said "We
continue to focus on achieving our long-term target of developing our
Segovia Operations to achieve a 200,000 ounce per year level. Due to
process issues at our Maria Dama plant, we have accelerated our planned
upgrades to the plant infrastructure and now expect to achieve a run
rate production of 1,000 tonnes per day in the fourth quarter, with the
completion of the work to achieve a maximum capacity of 1,500 tonnes
per day in early 2013. Upon completion of a proposed $100 million
project financing facility, we will move quickly to commence
development of the mine and construction of the new mill at Segovia.
At Marmato, while the Company continues to explore the impact of deep
zone mineralization on the options for the project, we continue working
closely with the community and other key stakeholders to build a strong
foundation for our development of the project."
Financial and Operating Summary
A summary of the financial and operating results for the second quarter
of 2012 is as follows:
|
|
Q2 2012
|
Q1 2012
|
Q2 2011(2)
|
|
Operating Data
|
|
|
|
|
Gold produced (ounces)
|
25,607
|
26,260
|
17,827
|
|
Gold sold (ounces)
|
24,418
|
24,814
|
17,533
|
|
Average realized gold price ($/oz sold)
|
$ 1,623
|
$ 1,676
|
$ 1,529
|
|
Total cash costs ($/oz sold) (1)
|
$ 1,313
|
$ 1,199
|
$ 1,409
|
|
Financial Data (x1,000 except per share amounts)
|
|
|
|
|
Total revenues
|
$ 40,737
|
$ 42,678
|
$ 27,725
|
|
Gross margin
|
$ 3,707
|
$ 7,921
|
($ 2,246)
|
|
Net income (loss) attributable to shareholders
|
($13,724)
|
($ 1,128)
|
($12,620)
|
|
Basic and diluted income (loss) per share
|
($ 0.04)
|
($ 0.00)
|
($ 0.04)
|
|
Cash and cash equivalents
|
$4,076
|
$ 5,113
|
$5,892
|
|
Total debt, including current portion
|
$85,554
|
$ 83,168
|
$7,180
|
|
(1)
|
|
"Total cash costs" are presented on a per ounce sold basis and represent
consolidated averages for the Company from both the Segovia Operations
and existing Marmato Underground mine. See "Additional Financial
Measures" in the MD&A.
|
|
(2)
|
|
Represents 4,378 ounces of gold ounces produced at the Marmato
Underground mine in the second quarter of 2011, prior to the merger
with Medoro on June 10, 2011.
|
Segovia Operations Update
In the second quarter of 2012 production at the Segovia Operations
totalled 20,610 ounces of gold with an average daily processing rate of
591 tonnes of ore per day ("tpd"), compared to 20,637 ounces of gold
with an average daily processing rate of 509 tpd in the first quarter
of 2012.
The Company is in the process of upgrading the Maria Dama plant to
achieve a maximum capacity of 1,500 tpd. The first phase of the
expansion plan was expected to enable the Company to ramp production up
to 1,000 tpd early in the second quarter of 2012, double the historical
processing rate at Maria Dama. The new ball mill came on-line in
mid-May and was tested over the weeks to follow under increasing loads.
After experiencing some delays related to power supply interruptions
due to problems at EPM's La Cruzada substation, together with the
mill's motor bearings overheating due to misalignment problems, and
subsequent delays due to temporary problems with the original crusher,
the mill proved to be able to handle loads of 1,000 tpd. For the month
of June 2012, the processing rate at Maria Dama reached an average of
737 tpd, however, as mill throughput increased in May and June, mill
recovery rates decreased below historical levels, averaging only 86
percent for the second quarter of 2012 or about 10 percent lower than
the first quarter of 2012. Despite earlier metallurgical consulting
opinions that the flotation cells could handle the initial ramp up to
1,000 tpd, subsequent analysis showed that the capacity of the existing
flotation cells was insufficient to handle the increased volumes
combined with the exceptionally higher grade ore delivered by the
artisanal miners during the latter half of the second quarter.
The Company has accelerated plans to implement the second phase of the
Maria Dama expansion which includes the installation of six additional
flotation cells, the first two of which should be in operation in early
September and the other four during October. While these new flotation
cells are being installed, the Company is limiting mill throughput to
approximately 800 to 900 tpd to maintain mill recovery rates between 80
percent and 85 percent, and starting in October, to ramp up mill
throughput to 1,000 tpd with mill recovery rates expected to improve to
90 percent.
The completion of the Maria Dama expansion activities in 2012 to deliver
a maximum capacity of 1,500 tpd will enable the Company to increase
Segovia's production in 2013 to between 120,000 and 140,000 ounces of
gold. Since the existing Maria Dama mill expansion is fully funded from
existing cash balances, operating cash flow and local Colombian bank
debt, any delay in closing the proposed $100 million debt financing
will not have an impact on the Company's ability to increase its gold
production at the Segovia Operations in 2012 and 2013 as planned.
Upon closing of a proposed $100 million debt financing, the Company will
commence with development of the new mechanized mine and construction
of the new 2,500 tpd mill at its Segovia Operations. The capital cost
of the mill and mining equipment to be acquired for this expansion
project is currently estimated to cost approximately $100 million and
it is expected the capital costs will be spent over an approximately
18-month period following closing of the financing. Gold production
will commence within 12 months of commencing the project and the new
2,500 mill will be commissioned for operation toward the end of the
18-month period. At that time, the Company expects that the Maria Dama
mill may then be dedicated toward the processing of the higher grade
ore from the artisanal miners at Segovia.
Marmato Project Update
At the Marmato Underground Operations, an average of 740 tpd was milled,
producing 4,997 ounces of gold during the second quarter of 2012.
Mining operations encountered some lower grade ore zones that resulted
in a decrease in average head grades to 2.66 g/t in the second quarter
of 2012 and contributing to the 11 percent decrease in the second
quarter's gold production compared with the first quarter of 2012. Head
grades for the second half of this year are expected to be
approximately 2.9 g/t while throughput will be increased to an average
of 750 tpd.
Gran Colombia commenced work on a prefeasibility study of the Marmato
Project in 2011 to examine a number of feasible development options for
mining, processing and mine waste management to provide the foundation
for decision making for the optimum development of the project. The
options include stand-alone open pit mining, modern underground mining
and a phased combination of both open pit and underground mining. As a
result of the newly discovered deep zone mineralization that is open at
depth with increasing grades, the Company decided to delay completion
of the prefeasibility study while its explores the significance of this
high grade deep zone mineralization and its impact on the Company's
options for the development of the Marmato Project.
Outlook
The Company now expects 2012 gold production is expected to be between
113,000 and 123,000 ounces, including production at its Segovia between
90,000 and 100,000 ounces and approximately 23,000 ounces from its
Marmato Underground Operations.
The Company's longer term plan remains on track to reach a production
rate of 200,000 ounces of gold annually at its Segovia Operations by
2014.
Webcast
As a reminder, the Company will host a conference call and webcast on
Wednesday, August 15, 2012 at 9:00 a.m. Eastern Time (8:00 a.m. Bogota
time) to discuss the results and provide an operational update.
Webcast and call-in details are as follows:
|
Live Event link:
|
|
|
http://www.media-server.com/m/p/4atck4v9
|
|
Toronto & International:
|
|
|
1 (847) 585-4405
|
|
North America Toll Free:
|
|
|
1 (888) 771-4371
|
|
Colombia Toll Free:
|
|
|
01 800 9 156 924
|
|
Conference ID:
|
|
|
33064686
|
A replay of the webcast will be available at www.grancolombiagold.com
from August 16, 2012 until September 16, 2012.
About Gran Colombia Gold
Gran Colombia is a Canadian-based gold and silver exploration,
development and production company with its primary focus in Colombia.
Gran Colombia is currently the largest underground gold and silver
producer in Colombia with several underground mines in operation at its
Segovia and Marmato Operations. In addition, Gran Colombia is advancing
a project to develop a large-scale, gold and silver mine at its Marmato
operations.
Additional information on Gran Colombia Gold can be found on the
Company's website at www.grancolombiagold.com and by reviewing the
Company's page on SEDAR at www.sedar.com.
This news release contains "forward-looking information", which may
include, but is not limited to, statements with respect to the future
financial or operating performance of the Company and its projects.
Often, but not always, forward-looking statements can be identified by
the use of words such as "plans", "expects", "is expected", "budget",
"scheduled", "estimates", "forecasts", "intends", "anticipates", or
believes" or variations (including negative variations) of such words
and phrases, or state that certain actions, events or results "may",
"could", "would", "might" or "will" be taken, occur or be achieved.
Forward-looking statements involve known and unknown risks,
uncertainties and other factors which may cause the actual results,
performance or achievements of Gran Colombia to be materially different
from any future results, performance or achievements expressed or
implied by the forward-looking statements. Factors that could cause
actual results to differ materially from those anticipated in these
forward-looking statements are described under the caption "Risk
Factors" in the Company's Annual Information Form dated as of March 28,
2012 which is available for view on SEDAR at www.sedar.com. Forward-looking statements contained herein are made as of the date of
this press release and Gran Colombia disclaims, other than as required
by law, any obligation to update any forward-looking statements whether
as a result of new information, results, future events, circumstances,
or if management's estimates or opinions should change, or otherwise.
There can be no assurance that forward-looking statements will prove to
be accurate, as actual results and future events could differ
materially from those anticipated in such statements. Accordingly, the
reader is cautioned not to place undue reliance on forward-looking
statements.